We are working in-house on the production of the newest Scania building.

In addition to supplying and assembling the steel construction for this new building, we also produce and conserve the trusses that will be placed in the new Scania hall.

Six phases

The trusses will be delivered in six phases. The first phase consists of trusses of 18×2.5m. At Scania, the trusses will be placed in a new hall of approximately 6000 m². In week 27 the transport of phase 1 will take place, after which the other phases will soon follow. The entire hall is expected to be completed by the end of 2022.

We thank Salverda construction for this wonderful assignment!