Datacenter Switch

The project

In Diemen we build two new halls for Switch Datacenters. For this wonderful project we will deliver, produce and assemble the steelwork. All processed steel is pre-blasted and provided with a two-component epoxy coating.  

The work

The construction of the first hall started in March 2022. The steel for this stage was assembled on site within 5 weeks. Our sister company Kamplacon provided the new hall with roof- and wall cladding. At the beginning of November, the firewall was installed. Then, we started the assembly work. Phase 2 is currently built. Our assembly workers are assembling all the steel and will hand over the construction to Kamplacon within a short period of time.

Continuation

The installation work is in the final phase. It is expected, that the new Switch datacenter will be completed at the beginning of 2023.